Just completed the installation of new step-up generator transformer 25 MVA ratio 10/132 kV at Castelletto Hydro Power Plant (Vittorio Veneto - Treviso) which belongs to ENEL.
SEA has performed in this plant the replacement of old unit "turn key" for the client, with direct arrangement and supervision of following activities:
- disconnection at HV and MV side of old unit
- removing of old unit
- transport, unloading and positioning of new 25 MVA
- reconnection at HV and MV side
- remounting of fance and fire-extinguishing plant
Castelletto Power Plant (italy)
10 April 2008